English | Select | |
한국어 | Select | |
Русский | Select |
Project : Ichthys CPF and FPSO Project
Site : Australia
Shipyard : SHI / DSME
Engineering : SUNBO
End-user : INPEX
Delivery : 4Q. 2014(CPF) / 2Q. 2014(FPSO)
Size : 6m(W)x5m(L)x4m(H)1set and other 1set
Weight : 10.7 / 6.2 Ton
Scope of Work : Basic/Detail/Shop/Field Fabrication Drawings
Procurement all of materials and Electric heater
Fabrication of Equip, piping, stru.
and unit assembly
Final Vendor Documents
3D Modeling and Others
Main Material : Structure : 355J2
Piping : Duplex, SS316L
Equipment : 316L
Remark : EEHA Installer is available